Estimating in Steps
Get an idea about giving the best estimates of an Agile project.
Steps for project planning
In our opinion, a good estimate for a reliable quote or a good one. The project plan consists of the following four steps:
Requirements gathering
Set the preliminary requirements for the project for now because new requirements will emerge and existing requirements will change during the project. Always give an estimate with a margin at the start of a project. Note that the degree of uncertainty, and hence the margin, decreases during the project. There’s actually only one moment when the margin is zero. This is at the end of the project.