Solution: Parallel Courses III

Discover how to calculate the minimum months required to finish a set of courses with prerequisites by applying topological sorting on a directed acyclic graph. This lesson teaches you to build dependency graphs, manage in-degree counts, and use a queue to process courses efficiently. You'll understand how to update completion times and solve scheduling problems relevant for coding interviews.

Statement  

You are tasked with determining the minimum time required to complete a set of courses, given their prerequisite relationships and individual durations.

There are n courses labeled from 1 to n. The prerequisite relationships between these courses are provided as a 2D integer array relations, where each entry relations[j]=[prevCoursej,nextCoursej]\text{relations}[j] = [\text{prevCourse}_j, \text{nextCourse}_j] ...